Granite Dells Parkway Traffic Interchange Project
Construction Schedule for the week of August 30-September 3, 2010:
- Continue work with headwalls and catch basins
- Pave various locations on both ends of bridge and tie roundabouts and guardrail to bridge
- Finish curb tie ins throughout project
- Continue with seeding and erosion control throughout project
- Continue with landscaping of both roundabouts and landscape rock
- Set barrier transitions on bridge
- Prep the bridge for painting
- Prepare and set permanent signs throughout project
- Continue electrical work throughout project
- Motorists traveling along Highway 89A throughout the week, need to be aware, as periodic, one-lane closures (each direction: eastbound and westbound) will and can occur from August 30-September 3
- Motorists can expect a detour for eastbound and westbound traffic as a result of Highway 89A being closed from 7:00 PM – 12:00 AM on Monday, August 30 so crews can remove the concrete barriers. Please use caution throughout detour.
Please Visit PHOTOS to see Progress
|
|
Granite Dells Parkway Traffic Interchange Project
Construction Schedule for the week of August 23-27, 2010:
- Continue work with headwalls and catch basins
- Set transition barriers along bridge
- Pave bridge
- Finish curb tie ins throughout project
- Continue with seeding/landscaping throughout project
- Continue electrical work throughout project
- Motorists traveling along Highway 89A throughout the week, need to be aware, as periodic, one-lane closures (each direction: eastbound and westbound) will and can occur from August 23-27
Please Visit PHOTOS to see Progress
|
|
|
|
|